Home » Case » Case » Planning a Malt Whisky Distillery in Israel: Evaluating Copper Pot Stills and a Complete Equipment Package

Planning a Malt Whisky Distillery in Israel: Evaluating Copper Pot Stills and a Complete Equipment Package

Author: Henry Chen     Publish Time: 2026-11-25      Origin: Cassman

A copper pot still is often the most visible part of a malt whisky distillery. But for a buyer investing in a complete plant, its appearance is only one part of the decision.

In a recent inquiry for a proposed malt whisky distillery in Israel, a prospective customer asked Cassman to evaluate a double-distillation system with a 2,500L-charge wash still and a 1,600L-charge spirit still. The requested scope also covered mashing, fermentation, spirit collection, a smaller gin still, cask filling, utilities, controls, factory testing, shipping and installation supervision.

The buyer had seen our copper whisky pot stills online. Rather than requesting a catalogue price, they asked for an itemised quotation, copper specifications, an explanation of the pressure-vessel code used where applicable, and evidence of comparable stills and operating reference projects.

That combination of questions reveals the real purchasing requirement: a technically coordinated distillery package whose materials, manufacturing quality, delivery scope and operating references can be checked before an order is placed.

Planning a Malt Whisky Distillery in Israel: Evaluating Copper Pot Stills and a Complete Equipment Package

The Preliminary Equipment Scope

Process area

Requested equipment or service

Mashing

Mash tun designed around a 500kg grist load, hot liquor tank and wort cooler

Fermentation

Six 3,000L washbacks

Whisky distillation

Copper wash still with a 2,500L charge and copper spirit still with a 1,600L charge

Spirit handling

Spirit safe and receivers

Additional production

300L gin still

Cask operations

Cask filling station

Plant integration

Utilities, pumps, pipework and PLC control

Electrical

Electrical equipment suitable for the defined hazardous areas in the still house; site supply stated as 400V/50Hz

Delivery and service

Factory acceptance testing in China, shipment to an Israeli port and installation supervision in Israel

These are the customer's preliminary requirements, not a finalized Cassman specification. The inquiry refers to a detailed RFQ and process documents, but those attachments are not reproduced here. Final equipment tags, connections, performance figures and compliance scope must be checked against the actual project documents.

The Center of the Project: Two Copper Pot Stills That Work as a System

The requested stills are specified by charge volume, not simply by nominal vessel size. That distinction matters when evaluating operating capacity and comparing quotations.

In a malt whisky process, the wash still and spirit still have different roles. Their sizes and operating schedules must be assessed together with:

  • The volume and strength of wash available from fermentation

  • The intended number of distillation runs

  • Heating and cooling capacity

  • Low wines and feints handling

  • The customer's preferred spirit character and cut strategy

  • Cleaning and turnaround time between runs

A quotation that gives prices for two stills without explaining how material moves between them would leave an important part of the project unresolved. Our process review would therefore trace the route from washbacks through the wash still, intermediate receivers, spirit still, spirit safe and onward to spirit collection and cask filling.

The smaller 300L gin still should also be treated as a separate operating system within the overall project. Its botanical arrangement, heating method, condenser and cleaning requirements depend on the intended gin process. Including its price as a line item is not the same as confirming its final process specification.

Copper Thickness: Specify Each Component, Not Just “Copper Stills”

One of the buyer's most direct questions concerned copper thickness for the pot, neck and lyne arm.

This is a useful way to compare offers. “Copper pot still” describes a broad product category; it does not tell the buyer the thickness or construction of each part.

A technical proposal should identify, for each still as applicable:

  • The material and specified thickness of the pot body

  • The material and specified thickness of the neck

  • The material and specified thickness of the lyne arm

  • The construction and thickness of other relevant copper components

  • Product-contact materials used in fittings and associated pipework

  • The fabrication drawings and inspection methods applicable to the agreed design

Thickness should be stated on approved drawings and in the equipment specification. No copper-thickness figure is claimed in this article, because it has not yet been established for this customer's final design.

The same discipline applies to the buyer's question about a pressure-vessel code. Different parts of a distillery may have different design conditions: an atmospheric-process vessel, a steam-heated jacket, a pressurised utility component and a receiver should not automatically be treated as though the same code applies to all of them. The final proposal must state the design basis and applicable code or standard for each relevant component, along with its design pressure and temperature where required.

Check the Relationship Between Mash Size, Washbacks and Still Charges

The proposed plant includes a mash tun for 500kg of grist, six 3,000L washbacks, a 2,500L-charge wash still and a 1,600L-charge spirit still.

Those numbers provide a useful starting framework, but they do not establish an annual production capacity by themselves. Before confirming throughput, we would evaluate:

  • Expected wort volume and gravity from a 500kg grist load

  • Mash cycle time and the number of mashes required to fill a washback

  • Working volume versus total volume of each washback

  • Fermentation duration and expected wash strength

  • Wash-still run time and practical filling level

  • Spirit-still run time, cuts and receiver capacity

  • Operating days and staffing pattern

This review identifies potential bottlenecks before equipment is manufactured. For example, the mash system should be sized around the actual washback-filling schedule, while the stills should be assessed against the volume of fermented wash becoming available each week.

726640d7-434d-4ff4-8af6-d553eba317f8.jpg

Controls and Hazardous-Area Electrical Design

The inquiry requests PLC control and Ex-rated electrics in the still house. Those are related but distinct requirements.

A PLC system may manage selected temperatures, pumps, valves, alarms and process records. The customer should be told exactly what is automated and what still requires an operator. The final controls list should identify the instruments, control panels, software functions and interfaces included in the price.

Hazardous-area suitability requires a separate, site-specific review. It is not responsible to describe every motor or instrument as “explosion-proof” without a defined area classification. The equipment selection needs to be coordinated with the site's hazardous-area assessment, installation design and applicable Israeli requirements.

The stated 400V/50Hz supply provides an initial electrical basis. Before final selection, we would confirm the available site supply, connected and simultaneous electrical loads, and the location of panels and field devices relative to classified areas.

What “Complete Equipment Package” Should Mean

This request covers far more than the two whisky stills. To make an itemised quotation useful, the boundary of supply must be visible from grain processing through cask filling.

For the proposed scope, that means defining the supply and connections for:

  • Hot liquor preparation and mashing

  • Wort cooling and transfer to washbacks

  • Fermentation temperature management, if included

  • Wash transfer and distillation

  • Condensers and cooling-water circuits

  • Low wines, feints and finished-spirit receivers

  • The spirit safe and sampling arrangements

  • Gin production equipment and its separate process connections

  • Pumps, pipework, valves, instruments and PLC interfaces

  • Cask filling

  • Cleaning systems and site utilities

If a required service or piece of equipment is not included, it should be identified as a buyer-supplied item or a separately priced option. This makes the package easier to compare with competing quotations and reduces the risk of discovering missing connections during installation.

How We Would Structure the Quotation

The buyer requested prices per equipment tag number, together with FOB and CIF prices. We would organise the commercial offer around the approved RFQ equipment schedule so that each quoted item can be traced to a drawing or specification.

A practical quotation would distinguish:

  1. Equipment price by agreed tag number

  2. Included instruments, fittings and connections

  3. Optional equipment and recommended spare parts

  4. Factory testing and associated documentation

  5. Export packing

  6. FOB price at a named port

  7. CIF price at the agreed Israeli destination port

  8. Installation-supervision scope and associated travel costs

  9. Exclusions and buyer responsibilities

FOB and CIF should be stated with named ports and the applicable Incoterms edition. The quotation should also explain charges not covered by the selected term, such as destination handling, customs clearance, taxes, unloading or onward transport, as applicable.

The buyer also asked for lead time from drawing approval to shipment. That is a sensible milestone. Manufacturing time is more meaningful when the technical drawings, component selection and required documentation have been approved than when it is measured from an early inquiry date.

No prices or lead times are stated in this article; both require an agreed scope and production schedule.

Factory Testing, Inspection and Export Packing

The customer wants a factory acceptance test (FAT) in China. This creates an opportunity to agree on the checks before manufacturing begins.

Depending on the approved design, an FAT plan may cover:

  • Equipment identification against the tag schedule

  • Key dimensions and material specifications

  • Weld and surface-finish inspection

  • Applicable pressure or leak tests

  • Pump, valve, instrument and control checks

  • PLC/HMI functions that can be tested at the factory

  • Documentation review

  • Punch-list recording before release for shipment

Some process performance tests will still require the final site utilities, ingredients and operating conditions. The parties should therefore distinguish factory-test criteria from site commissioning criteria rather than assume a factory test proves everything.

Export packing is another part of product quality. A quotation should specify how copper surfaces, protruding connections, instruments, electrical cabinets and other vulnerable parts will be protected and marked for shipment. Packing photos and a packing list can help the receiving and installation teams identify equipment and check its condition on arrival.

References and Factory Verification: Evidence Should Be Specific

The buyer requested three whisky distilleries outside China operating with the supplier's stills, along with contact details. They also asked for photos and videos of comparable completed stills and a live factory video call.

These requests should not be answered with generic marketing material. A useful response would distinguish:

  • A still that has been manufactured

  • A still that has been shipped

  • A still that has been commissioned

  • A whisky distillery that is operating with the still

Reference details and direct introductions should be shared only where the reference customer has agreed. Photos and videos should be accurately identified, while a live factory call can help the buyer inspect current manufacturing activity and discuss construction details with the team.

This article does not claim that three qualifying references are already available. Any such claim should be made only after the projects and permission to share contact information have been verified.

Installation Supervision in Israel: Define the Responsibility Boundary

The inquiry asks for installation supervision, not necessarily a supplier-performed turnkey installation. That difference should be clear in the commercial offer.

Before shipment, the parties should agree who is responsible for:

  • Unloading, lifting and positioning

  • Foundations and floor preparation

  • Process piping and field welding

  • Electrical installation and hazardous-area work

  • Water, drainage, heating and cooling connections

  • Local inspections and permissions

  • Dry checks, wet commissioning and trial runs

  • Operator training

Cassman's proposed on-site personnel, duration, daily scope, travel costs and any conditions for commissioning should be stated separately. Local work should be carried out by appropriately qualified contractors in accordance with applicable site requirements.

The Value of a Verifiable Proposal

This project illustrates why serious distillery buyers ask detailed questions early. A copper still can be photographed; its construction, operating fit and long-term maintainability need documentation.

The strongest proposal for this inquiry would bring together:

  • Product: individually specified copper stills and supporting equipment

  • Design: a coordinated mash-to-cask process and realistic throughput review

  • Customisation: agreed charge volumes, still arrangement, controls and site interfaces

  • Quality: approved drawings, inspection points and a documented FAT

  • Compliance: component-specific design bases and a defined hazardous-area responsibility

  • Packing: protection and identification suited to international shipment

  • Price: itemised tag-level scope, named delivery terms and visible exclusions

  • Service: an agreed division of installation, commissioning and training responsibilities

At present, this is a prospective inquiry, not a delivered case study. The next step would be to review the buyer's full RFQ, process flow, equipment schedule and still arrangement, then issue a technical proposal and itemised preliminary quotation against those documents.

Planning a malt whisky distillery? Share your process requirements, site utility information and equipment schedule with Cassman. We can help you assess how the stills and the rest of the plant should work together before you commit to a final configuration.

Planning a Malt Whisky Distillery in Israel: Evaluating Copper Pot Stills and a Complete Equipment Package

Frequently Asked Questions

Why ask for copper thickness in different parts of a whisky pot still?

The pot, neck and lyne arm are distinct components. Specifying each one separately makes the construction and quoted scope easier to verify and compare.

Do a 2,500L wash still and 1,600L spirit still establish production capacity?

Not by themselves. Throughput also depends on wash strength, practical charge levels, run times, cuts, heating and cooling capacity, and the fermentation schedule.

Does “Ex-rated electrics” mean every electrical component must have the same rating?

No. Equipment selection should follow the site's defined hazardous-area classification and the location and function of each component.

What is the difference between FOB and CIF in a distillery quotation?

They allocate transport-related costs and responsibilities differently. Both should name the relevant port and Incoterms edition, with destination charges and other exclusions clearly identified.

Can a factory acceptance test prove the whole distillery will meet its site production target?

Not on its own. An FAT checks agreed items that can be inspected or tested at the factory. Site-dependent performance must be addressed through commissioning and separately agreed acceptance criteria.

Ready to Build Your Brewery with a Trusted Partner?

Don't navigate the world of brewery manufacturing alone. Let my team of experienced engineers provide you with a no-obligation quote and a preliminary design for your project.
Contact us
​Jinan Cassman Machinery Co., Ltd. is mainly engaged in beer equipment, whiskey distillery equipment, biological fermentation, and environmental protection equipment, among others.​

Quick Links

Product Category

Contact Us

Email: inquiry@cassmanbrew.com

Tel: 0086 531 88822515

Mobile/Whatsapp/Wechat: +86 18560016154

Factory Address: No.3-1, Weili Industrial Park, Qiliu Road,Qihe County, Dezhou City. Shandong. China.

 
Copyright © 2025 Jinan Cassman Machinery Co., Ltd.All Rights Reserved. Sitemap