Your brewery equipment has passed its factory acceptance test. The tanks have arrived, the control panel is on site, and installation is underway.
Is the brewery ready for its first commercial batch?
Not yet. A successful factory acceptance test (FAT) shows that agreed equipment and functions passed checks at the manufacturer’s facility. It cannot confirm that the brewery will operate correctly after being connected to your building’s water, power, steam, glycol, compressed air and drainage systems.
That is the purpose of commissioning and site acceptance testing (SAT): to turn delivered equipment into a safe, functional production system—and to document which performance requirements have actually been met.
This guide provides a practical commissioning framework for a 10HL craft brewery. It is particularly useful for buyers coordinating an overseas equipment supplier, local contractors and their own brewing team.
Before the first commercial brew, a 10HL brewery should pass a documented sequence of checks covering:
Equipment placement and installation
Utility connections
Piping and valve identification
Electrical safety and control-system checks
Water-based functional tests
Steam and heating-system checks, where applicable
Glycol and wort-cooling checks
CIP system checks
Tank and cellar-control checks
Operator training
A supervised trial brew
Closure of critical defects and formal handover
Commissioning should follow the approved design, equipment manuals, applicable local regulations and a project-specific test plan. Do not treat a generic checklist as authorization to operate pressure, electrical, steam or chemical systems without qualified personnel.
These terms are related, but they describe different milestones.
Milestone | Where it happens | Main question |
Factory acceptance test (FAT) | Manufacturer’s facility | Was the agreed equipment built, documented and tested as far as practical before shipment? |
Installation | Customer’s site | Has the equipment been placed and connected according to the approved design? |
Commissioning | Customer’s site | Do the installed components and systems operate correctly together? |
Site acceptance test (SAT) | Customer’s site | Have the agreed on-site acceptance criteria been demonstrated and documented? |
Commercial operation | Customer’s brewery | Can trained operators run production under the brewery’s approved procedures? |
Passing FAT does not automatically mean passing SAT. Equally, completing one trial brew does not necessarily prove that every contracted performance requirement has been met.
The buyer and supplier should agree on these distinctions before shipment.
A brewery project typically involves several parties:
Equipment manufacturer
Local mechanical installer
Electrician
Steam or boiler contractor
Refrigeration contractor
Building contractor
Brewery owner
Head brewer and operators
If responsibilities are unclear, a simple problem can turn into a costly dispute. For example, a pump may be fully functional, but it cannot achieve the expected flow because a field-installed pipe is undersized. A chiller may be correctly specified, but the available electrical supply differs from the project information supplied before purchase.
A commissioning plan should therefore identify:
What will be tested
Who performs the test
What conditions must be available
What counts as a pass
How results will be recorded
Who corrects a failed item
The goal is not paperwork for its own sake. It is to ensure that the brewery can move from installation to production without relying on assumptions.
On-site commissioning is most effective when the building and utility connections are ready before the supplier’s technicians travel.
Confirm that the following are complete or available:
Approved equipment layout and sufficient access around vessels
Floor capacity and finished floor levels verified by the appropriate local professionals
Equipment positioned, leveled and secured as required
Drains installed and tested
Potable/process water available at the agreed pressure and flow
Electrical supply installed and checked by qualified local electricians
Steam system installed and approved where applicable
Glycol system installed and filled according to its approved procedure
Compressed-air supply and treatment installed
Ventilation and exhaust systems available
Internet connection available if remote support is included
Local permits, inspections and authorizations arranged
Cleaning chemicals, raw materials and trained staff available when needed
Do not schedule a full commissioning visit around an unverified “installation complete” date. Request a pre-commissioning site-readiness review, supported by photographs, drawings and utility measurements where appropriate.
Start by comparing the installed brewery with the approved general arrangement drawings and equipment list.
Check:
Vessel tags and locations
Service access to manways, valves and pumps
Platform installation and safe access
Clearance for maintenance and component removal
Pipe supports and routing
Floor-drain access
Tank leveling
Protection of electrical equipment from washdown areas
Accessibility of emergency stops and isolation points
A brewery can be mechanically complete yet difficult to operate or maintain. Installation should be assessed for safe daily use, not only whether everything fits in the room.
If you are still planning a building rather than commissioning one, CASSMAN’s Blog includes articles on brewery layout and utility planning.
The commissioning team should record the actual site conditions, not rely solely on figures provided during the quotation stage.
Verify the required:
Supply pressure
Available flow rate
Water quality or treatment status
Hot and cold supply connections
Drainage capacity
Qualified personnel should verify:
Supply voltage and frequency
Phase configuration
Protective devices
Grounding/earthing
Motor rotation
Panel labeling
Isolation procedures
Qualified contractors should verify:
Steam-generator installation and local approvals
Supply pressure
Pressure-reduction arrangement
Steam traps and condensate handling
Line insulation
Safety devices
Leak-free distribution to the specified users
Check:
Fluid preparation according to the chiller and process requirements
Supply and return identification
Pump direction
Flow through connected tanks
Insulation and condensation control
Air removal from the circuit
Available cooling performance under the agreed test conditions
Confirm:
Operating pressure at the equipment
Available flow
Receiver and treatment equipment
Filtration and dryness appropriate to the intended use
Stable pneumatic valve operation during simultaneous demands
Where air or gas can contact product or product-contact surfaces, its quality requirements should be separately defined and verified.
A P&ID is most valuable when it reflects what is actually installed.
Walk through the system with the approved drawing and verify:
Vessel tags
Pipe destinations
Flow directions
Pump locations
Manual valve tags
Pneumatic valve tags
Instrument locations
Sample points
CIP supply and return paths
Drains
Steam and condensate lines
Glycol supply and return lines
Record any difference between the drawing and the installed system. If a field change is accepted, update the as-built documentation before handover.
An incorrect or outdated P&ID can lead to:
Operating mistakes
Incorrect cleaning routes
Troubleshooting delays
Poor spare-parts identification
Confusion during future expansion
A complete installation is not fully handed over until the brewery has usable, accurate documentation.
Before using wort or cleaning chemicals, perform the applicable functional checks with water under a controlled test plan.
Confirm:
Pumps run in the correct direction.
Pumps start and stop from the specified controls.
Flow travels through the intended route.
Valves open and close as commanded.
Valve-position feedback is correct where fitted.
Flowmeters display sensible values.
Temperature sensors identify the correct vessels.
Level and pressure signals display correctly.
Leaks are identified and corrected.
The team should also test expected failure responses. For example, if a pump is designed to stop when a receiving vessel reaches a defined level, that interlock should be demonstrated under a safe test condition.
Do not assume that a successful control-panel simulation during FAT proves every field-installed component has been wired and connected correctly.
For an automated 10HL brewery, controls are not “commissioned” merely because the HMI turns on.
The commissioning team should check the agreed functions on the actual installed equipment:
Manual and automatic operating modes
Recipe creation and selection
Multi-step mash temperature control
Pump commands
Pneumatic valve sequences
Flowmeter display and relevant control functions
Temperature setpoints
Alarm messages and alarm history
Trend or process-curve recording
Data logging
User permissions
Safe recovery after an interruption
Where practical, run sequences first with water and controlled operating conditions. Confirm that the intended valve opens, the correct pump starts, the expected sensor is read and the sequence stops safely if a required condition is not met.
If future tank-control positions were included in the order, verify what was installed and document which functions remain inactive until the future tanks are added.
For overseas projects, remote access should also be tested and documented, including authorization and access-control arrangements.
A 10HL brewhouse designed for two brews per day depends heavily on its heating and hot-water recovery performance.
Under agreed test conditions, record relevant values such as:
Starting and target water temperatures
Heat-up time
Steam pressure or electrical demand, as applicable
Hot liquor tank recovery behavior
Temperature-control response
Safety shutdown behavior
The results should be compared with the contractual performance assumptions. If those assumptions did not specify starting water temperature, ambient conditions or simultaneous demand, resolve that gap before interpreting the result as a pass or failure.
A test performed with water provides useful evidence of heating performance. It is not identical to a production boil, which should be evaluated during a supervised brew where required.
For a two-brew-per-day project, wort cooling must work not only for the first batch but also within the timing required for the second.
The commissioning plan should identify:
Target wort volume
Inlet and outlet temperatures
Target transfer rate
Cooling-water conditions
Cold liquor starting conditions
Glycol conditions
Recovery time between transfers
Some performance can be checked with water, but final confirmation of the agreed wort-cooling result may require a supervised production test.
Do not judge the system solely by chiller horsepower. The result depends on the complete arrangement of the plate heat exchanger, incoming water, cold liquor storage, glycol system and site conditions.
For each fermenter and bright beer tank, verify:
Tank identification on the HMI
Temperature-sensor reading
Glycol valve operation
Cooling response
Alarm behavior
Pressure-related instruments and accessories as specified
Sample-valve and CIP-connection accessibility
Correct assignment of any tank-control recipes or setpoints
Pressure equipment should be operated within its approved design limits and in accordance with the applicable manuals and local requirements. Pressure-related checks and safety devices require the appropriate qualified personnel and documented procedures.
A simple but important test is to confirm that a command for FV-03 actually operates the cooling valve and reads the sensor belonging to FV-03. Point-identification errors can cause difficult-to-diagnose fermentation problems after startup.
A CIP system must be operational before the brewery can establish reliable cleaning procedures.
Verify the agreed equipment and functions, including:
Caustic, acid/disinfection and recovery tanks
CIP pump
Heating control
Level indications and protections
Supply and return paths
Drain routing
Valve positions
Temperature display
Safety interlocks
Then establish and approve site-specific cleaning procedures using:
Equipment manufacturer instructions
Chemical supplier instructions
Brewery hygiene requirements
Appropriate safety procedures
Verification methods
A successful water-routing test is not proof that every tank has been hygienically cleaned. Cleaning effectiveness should be verified through the brewery’s approved inspection and hygiene-monitoring program.
After installation checks and water-based testing are complete, conduct a supervised brew under a written test plan.
A trial brew can help verify the complete operational chain:
Malt handling
Mashing
Lautering
Kettle operation
Whirlpooling
Wort cooling
Transfer to the designated fermenter
Process data recording
Cleaning and reset
Record operating observations and deviations rather than relying on “the first brew went well” as the sole acceptance statement.
The test plan should define:
Whether both 10HL batches must reach fermenters on the same day
How batch volume is measured
Recipe assumptions
Available operators
Start and completion times
Cleaning time
Required utility conditions
Permitted interruptions
A two-brew performance claim should be judged against these agreed criteria—not against an informal demonstration under unspecified conditions.
Training should prepare the brewery team to run and maintain the system after visiting technicians leave.
A useful training plan includes:
Startup and shutdown
Manual versus automatic modes
Recipe changes
Valve and pump operation
Alarm interpretation
Emergency stops
CIP operation
Basic maintenance
Routine inspections
Troubleshooting and escalation
Remote-support procedures
Spare-parts identification
Ask the trainer to use the final installed system and its as-built documents. Where possible, have operators demonstrate key tasks back to the commissioning team. That is a better measure of training effectiveness than attendance alone.
Not every minor issue must necessarily prevent handover, but the status of every issue should be clear.
Maintain an open-item list showing:
Item number
Equipment tag
Description
Operational or safety impact
Responsible party
Corrective action
Retest requirement
Target completion date
Closure evidence
Safety-critical or production-blocking items should be resolved before the affected equipment is released for use. Any other outstanding work should be expressly agreed by the buyer and supplier.
The final handover package may include:
Signed commissioning and SAT records
Updated as-built drawings and P&ID
Electrical drawings
Equipment manuals
Maintenance instructions
Applicable certificates and test records
PLC/HMI backup arrangements, as agreed
Spare-parts list
Training records
Warranty and support contacts
Open-item closure plan
Area | Example acceptance question | Status |
Installation | Are vessels and platforms installed in approved locations? | Pass / Open |
Water | Are required supply conditions available and recorded? | Pass / Open |
Electrical | Have qualified personnel completed required checks? | Pass / Open |
Steam | Is the installed system approved and operating as specified? | Pass / Open / N/A |
Glycol | Do supply, return and tank controls function correctly? | Pass / Open |
Compressed air | Do pneumatic valves operate reliably under expected demand? | Pass / Open |
Piping | Do installed lines match the approved or updated P&ID? | Pass / Open |
Pumps and valves | Do commands operate the correct field devices? | Pass / Open |
PLC/HMI | Are agreed sequences, alarms and records functional? | Pass / Open |
CIP | Are routing, controls and protections functional? | Pass / Open |
Trial brew | Has the agreed trial-brew scope been completed? | Pass / Open |
Training | Have designated operators completed practical training? | Pass / Open |
Documentation | Are required as-built documents and manuals delivered? | Pass / Open |
The exact acceptance criteria should be specified in the purchase agreement or approved commissioning plan. “Pass” should be supported by a recorded observation, measurement or signed test result.
One of the most useful additions to a brewery contract is a responsibility matrix.
Work or deliverable | Supplier | Local contractor | Brewery owner |
Equipment drawings | Define scope | Use for installation | Review and approve |
Equipment placement guidance | Advise, if included | Perform rigging/installation | Provide access and site readiness |
Site electrical connection | Provide equipment requirements | Install and test locally | Provide compliant supply |
Steam-generator installation | Define supplied package | Install/approve as locally required | Arrange site utility and permits |
PLC commissioning | Perform or supervise if contracted | Support field wiring | Provide operators and access |
Trial brew | Support if contracted | Attend if needed | Provide ingredients and brewing staff |
Operator training | Deliver if contracted | — | Ensure staff attend |
Site acceptance sign-off | Submit test evidence | Submit local work records | Review and approve |
This is an example, not a default allocation of legal responsibility. The final division of work must be agreed for the project and destination country.
CASSMAN supplies brewery equipment and supports international projects with engineering drawings, installation guidance, commissioning and training arrangements according to the agreed project scope.
For a new 10HL brewery, early coordination is especially important. Before installation begins, the buyer and CASSMAN project team should align on:
Approved layout and P&ID
Site utility conditions
Scope of local contractors
Technician travel and site-readiness dates
FAT open items
Commissioning procedures
Training needs
SAT acceptance criteria
You can explore project examples on the CASSMAN Case Studies page and find related planning guidance in the CASSMAN Blog.
The first brew is an important milestone, but it should not be the first time the installed brewery is tested as a complete system.
A disciplined commissioning program moves in stages:
Confirm the site → inspect installation → verify utilities → test with water → commission controls and cellar systems → establish cleaning procedures → brew under supervision → document acceptance.
That approach helps protect the buyer’s investment, reduces avoidable startup delays and gives brewery operators a more reliable foundation for production.
The duration depends on equipment scope, automation complexity, site readiness, local contractor work and the agreed trial-brew requirements. Ask the supplier to provide an estimated technician count and schedule after reviewing the installation scope and utility readiness. A generic duration may not reflect your site.
Not always. Some quotations cover equipment supply only; others include remote guidance, on-site supervision, control-system commissioning or operator training. Request an itemized service scope showing technician numbers, estimated days, travel costs and buyer responsibilities.
Some projects use qualified local contractors supported remotely by the manufacturer. Whether that is appropriate depends on system complexity, controls, local capability and contract terms. Define who will perform testing and sign off each system before choosing this approach.
No. FAT checks equipment and functions that can be tested before shipment. Site utilities, field connections, complete process performance and operator training require commissioning and, where agreed, SAT.
A trial brew is an operating test using brewing materials. SAT is the contractually defined site acceptance process. A trial brew may form part of SAT, but SAT can also include utility measurements, safety checks, documentation and training.
Agree in advance on batch-volume definition, recipes, staffing, utility conditions, brew-day duration and the completion point for both batches. Then record performance during an agreed on-site test.
CASSMAN can discuss installation guidance, commissioning and training as part of a project-specific proposal. Confirm the exact scope, technician count, duration and responsibilities in the quotation and contract.
Building or expanding a craft brewery? Share your equipment list, site layout, utility information and target production schedule with CASSMAN.
Contact CASSMAN to discuss an installation, commissioning and training scope tailored to your brewery project.
Brewery Equipment Commissioning Checklist: From Installation to the First 10HL Brew
Brewery Equipment FAT Checklist: What to Test Before Your 10HL System Ships
How to Plan a 10HL Brewery for Two Brews per Day: A Complete Equipment and Utility Checklist
3-Vessel vs. 4-Vessel Brewhouse: Which Is Better for a 10HL Brewery Brewing Twice a Day?
How We Evaluate a 100,000-Bottle-Per-Month Whisky Distillery Project in Canada
How to Clean a Brewery Fermenter: A Simplified CIP Procedure for Small Craft Breweries
How Much Does It Cost to Start a Microbrewery? A 2026 Equipment and Budget Guide